Project Timeline
*This map is updated on April 2023 and is an artist's impression, indicative for illustrative purpose.
Stage 1 Civil Works: Works commenced in January 2021 and is now complete. The stage 1 civil works include:
- Site-preparation.
- Bulk excavation of the roadways.
- Bulk excavation of the basement for the first residential building MAC Residences.
- Bulk excavation of the basement for the Midtown by the Park precinct, including Soul Residences.
- Installation of services (High and low voltage electrical wiring, sewer, water, stormwater and communications).
- Construction of the first new roadways.
- Installation of public domain landscaping.
Stage 1 Construction: Commenced in September 2021 and is on track for completion in Q1, 2024. Stage 1 construction includes:
- Construction of our first residential building MAC Residences - 269 market apartments over 24 stories with ground floor childcare centre and three levels of the basement.
- Construction of the Midtown by the Park precinct - 103 market apartments, 4 market terraces, 130 affordable apartments, 259 community housing apartments, and three levels of basement.
Stage 2 Civil Works: Works commenced in July 2022 and is due to complete in Q4 2023. The stage 2 civil works include:
- Site-preparation.
- Bulk excavation and construction of the roadways.
- Installation of services (High and low voltage electrical wiring, sewer, water, stormwater and communications).
- Construction of the Shrimpton's Creek crossing bridge.
- Installation of public domain landscaping.
Stage 2 Construction: Development Approval has now been received and construction is anticipated to commerce in 2024. Stage 2 construction includes:
- Treehouse Apartments - Construction of 162 market apartments over 16 stories with ground floor retail and three levels of the basement. Completion scheduled for 2025.
- Central Village Green and Community facilities – Construction of a 3,300 sqm park with children’s playground, pool and gym facility, 700 sqm of community facilities with an indigenous community garden. Completion scheduled for Q1 2025.
- Future residential market and community housing apartments scheduled for completion in Q4 2026.
Stage 3 forecast completion Q2 2027
- Residential apartments.
- Shrimpton's creek rehabilitation.
- Part Endangered Ecological rehabilitation.
Stage 4 forecast completion Q3 2028
- Residential apartments.
- Forest playground.
- Part Endangered Ecological rehabilitation.
Stage 5 forecast completion Q1 2029
- Residential apartments.
- Part Endangered Ecological rehabilitation.
Stage 6 forecast completion Q2 2030
- Residential apartments.
- Part Endangered Ecological rehabilitation.
Stage 7 forecast completion Q4 2030
- Residential apartments.
- Part Endangered Ecological rehabilitation.
Disclaimer: Forecast completion dates are correct as at April 2023, dates outlined are subject to change due to development approvals or for other reasons outside Frasers Property’s control.
have a query or concern ?
If you have a query or would like to lodge a complaint, you can email or call us via the dedicated community phone number and email address. Call 13 38 38 or email midtowncommunityfeedback@frasersproperty.com.au You can also contact us via post - postal address: 1 Ivanhoe Place, Macquarie Park NSW 2113.